LEED
Sustainability is more than a buzz word; it is a thought process, a mantra, a team effort to design and build with the least environmental impact without sacrificing quality or aesthetics. To help clients achieve their sustainability goals, we staff a team of LEED-accredited professionals. These specialists can incorporate green building technologies, register a project for certification with the US Green Building Council (USGBC) and select LEED credits to pursue. They also help clients analyze cost and construction issues related to sustainable construction and coordinate all necessary documentation and preparation of submittals.

GlenLake VII
Raleigh, NC
132,461 SF Five-Story Class “A” Office with 1,066 Space Parking Deck
- LEED Certified
- Architectural precast concrete panels
- Curtain wall glass
- Loggia feature at building entrance
- Glass canopy connecting building and parking deck

Nexus at Waverly
Charlotte, NC
160,000 SF Six-Story Office Buliding with 718 Space Parking Deck
- LEED Certified
- Architectural precast with curtainwall
- Three-story parking deck
- Project site was tightly bordered by streets on three sides and a construction site on the other

Waverly Office Building
Charlotte, NC
160,000 SF 6-Story Office Building
- LEED Silver
- 4-story, 900 space parking deck
- Architectural precast with curtainwall
- Detailed logistics planning due to tight constraints around the site and neighboring residential area

Legacy Union
Charlotte, NC
1,005,000 SF 33-Story Office Tower
- Under Construction
- LEED Gold Goal
- 1,005,000 SF 33-story office tower building
- 4th tallest (640 feet) office building in Charlotte, NC
- 12 level pre-cast parking deck with 2,600 parking spaces
- Joint venture with Gilbane
- Located in Uptown near Bank of America Stadium
- Largest office and parking structure currently under construction in Charlotte, NC
- The Tower is the first in Charlotte’s biggest new uptown development in decades

Midtown Plaza
Raleigh, NC
343,854 SF
- LEED Silver
- 12-story core and shell office tower
- Two (2) 7-level precast parking decks with 1,020 parking spaces
- Deep foundations with auger cast piles
- Limited lay down area
- Design Build MEP
- Energy efficient glass providing maximum clarity/transparency
- Loading dock with dock levelers and security cameras
- Facade articulated by neutral and dark color precast concrete pads

Grifols E750 Administration Building
Clayton, NC
112,000 SF 3-Story Office Building
- LEED Silver
- Glass and metal panel skin
- Class “A” office interiors
- High end finishes in executive wing and atrium lobby
- Monumental lobby stair with precast terrazzo treads and stainless steel railings

Sealed Air Corporate Headquarters
Charlotte, NC
225,000 SF Class “A” Corporate Headquarters
- LEED Gold Office Building A & B
- LEED Gold Research & Development Lab
- 173,000 SF research and development lab\
- 225,000 SF office upfit
- Two (2) parking decks totaling 1,296 parking spaces
- 32 acre site

LPL Financial Office Complex
Fort Mill, SC
Two 6-Story Office Buildings with 6-Level Parking Deck
- LEED Gold
- 317,000 SF six-story office building with basement
- 150,000 SF six-story office building
- 585,000 SF six-level sandblasted textured parking deck
- 1,930 space parking deck

Capitol Towers
Charlotte, NC
480,000 SF
- LEED Gold North Tower
- LEED Gold South Tower
- Two (2) 10-Story Office Towers
- 7-story parking deck with 1,561 parking spaces
- 25,000 SF separate retail and restaurant building
- 5,350 SF ground floor retail space
- Six (6) acre site
- Phased construction

Lash Group Corporate Office
Fort Mill, SC
250,000 SF
- LEED Silver
- 5-story Class “A” office building
- Composite steel frame construction
- Brick inlaid architectural precast with curtainwall
- Design build MEP
- 30’ tall segmental retaining walls

Winston-Salem State University Hill Hall Student Success Center
Winston-Salem, NC
38,000 SF Adaptive Reuse and Expansion
- LEED Gold
- New two-story entrance lobby
- Building originally constructed in 1964
- CM at Risk
- Joint Venture with R.J. Leeper Construction
- Awarded “Certificate of Merit” by North Carolina State Building Commission

Kingsley VI
Fort Mill, SC
60,000 SF 3-Story Office Building Shell and Upfit
- LEED Certified
- Architectural precast veneer
- Eight (8) month schedule for shell and upfit

Environmental Way (EnergyWay)
Charlotte, NC
8,000 SF Core and Shell Renovation
- LEED Platinum
- Eco-X countertops throughout (recycled glass)
- Over 60% of all waste diverted from landfill
- Decorative 3-Form Eco Resin Panels
- Locker rooms consisted of recycle glass terrazzo tile

Piedmont Federal Savings Bank
Winston-Salem
60,000 SF 5-Story Class "A" Office Building
- LEED Certified
- Corporate headquarters
- Operations center
- 3,500 SF branch bank

High Point University School of Education
High Point, NC
31,000 SF Two-Story Classroom
- LEED Silver
- Georgian-style structure
- Library, resource center, study lounge, office and computer labs

NC State University Carol Johnson Poole Golf Clubhouse
Raleigh, NC
30,000 SF 2-Story Golf Clubhouse
- LEED Silver
- Located on NC State University’s Centennial Campus
- Includes dining room, locker rooms, pro-shop, coaches offices and golf cart storage
- Nine (9) month fast track schedule

8740 Research Drive
Charlotte, NC
160,000 SF, Four-Story Upfit
- LEED Silver
- Parking lot full depth reclamation
- New employee patio and garden wall
- Expanded main lobby
- Employee shower/locker rooms

Biologics Office Building
Cary, NC
79,000 SF
- LEED Certified
- 3-story core and shell office building and full tenant upfit
- Pre-action server room
- Fitness center
- 350+ surface parking lot
- BMP pond
- Greenway trail

GlenLake V Office Building and Parking Deck
Raleigh, NC
172,100 SF
- LEED Certified
- 6-story Class “A” Office Space
- 4-story parking deck with 634 spaces
- 2,000 SF fitness center with locker facilities
- 1,000 SF indoor/outdoor entertainment space
- 2,000 SF collaborative lobby with lounge area and cafe area
- Outdoor plaza and courtyard with canopy

Deutsche Bank
Raleigh, NC
25,000 SF Fit Up
- LEED Gold
- Software design center
- Data center component
- High level finishes
- Full data and Audio Visual infrastructure
- Project completed in 9 weeks
- Tier II

U.S. Citizen and Immigration Services Building
Durham, NC
27,100 SF Office Space
- LEED Silver
- Computerized Energy Management System and Controls
- Building security system
- Two-story porcelain tile lobby at entrance
- High ceiling training/ceremony room
- 2 hydraulic elevators

Independence Corporate Park Building 7
Greenville
83,000 SF Class “A” Office Building
- LEED Silver
- Factory Mutual Coordination
- Complex masonry project
- Unique, high-end interior lobby finishes
- Design build MEP
- Fourth project for Owner in two (2) years
“I was very clear with the problems and issues we had encountered with our two previous construction projects with a different contractor, and was not convinced this project with Shelco would be any different. You promised me this project would be seamless, and now I am a true believer.”
—Cyndy White
Administration Manager
NOBEX